| Location | ||
| 1 | State | Karnataka |
| 2 | District | Raichur |
| 3 | Taluk | Devadurga |
| 4 | Canal | D18 of NRBC |
| 5 | Location of D18 | On left bank at Ch: 94.960 KM of NRBC |
| 6 | Nearest Village | Agrahara (2km) on right bank. |
| 7 | Nearest Town | Devadurga (10km) |
| 8 | Nearest City | Raichur |
| 9 | Air- Port | Bangalore - About 450 km Hyderabad - About 200 km |
| Purpose of the Project | ||
| 1 | Purpose of the Project | Generation and Transmission of Hydro Electric Power |
| Installed Capacity | ||
| 1 | Installed Capacity | 1 x 925 kW |
| Annual Energy Generation | ||
| 1 | Annual Energy Generation | 5.28 GWHr |
| Power Studies | ||
| 1 | Minimum Design Power Discharge | 2.865 cumecs/ Unit, at rated head |
| 2 | Maximum Design Power Discharge | 9.55 cumecs / Unit |
| 3 | Overload | 10% |
| 4 | Maximum Discharge | 10.51 cumecs / unit |
| Diversion Weir | ||
| 1 | Location | Weir across D18 CH:4880.0m, near upstream of Drop 2 |
| 2 | Type | Gated, Gravity section built out of mass concrete |
| 3 | FRL | El 436.50 m |
| 4 | Weir Crest | El 435.50 m |
| 5 | Top of NOF | 437.40 m |
| 6 | Deepest Foundation level | El 429.96 m |
| 7 | Height of the Weir up to crest (from deepest foundation level) | 5.54 m |
| 8 | Length of Overflow Section | 7.2 m |
| Non Overflow Block | ||
| 1 | Left | 10.79 m |
| 2 | Middle | 14.49 m |
| 3 | Right | 13.76 |
| Total of NOF | 39.04 m | |
| Intake | ||
| 1 | No of Vents | 1 |
| 2 | Vent Size | 4.113 m x 2.623 m |
| 3 | Sill Level | 429.19 m |
| 4 | Hoist Bridge Level | 437.40 m |
| 5 | Gates | |
| (a) Service Gate | ||
| Nos. | 1 | |
| Size | 4.113 m x 2.623 m | |
| Type | Vertical lift roller gate | |
| Hoist | Under Slung Monorail | |
| (b) Stop log Gate | ||
| Nos. | 1 | |
| Size | 4.113 m x 8.49 m | |
| Type | Vertical lift roller gate | |
| Hoist | Under Slung Monorail | |
| (c) Trash Rack | ||
| Nos. | 1 | |
| Size | 4.113 x 8.49 m | |
| Hoist | Under Slung Monorail. | |
| Power House | ||
| 1 | Location | On right bank of D18 near drop 2 at Ch: 4900m |
| 2 | Type | Surface type |
| 3 | Size of Machine Hall (Outer to Outer) | 8.90 m x 14.132 m |
| 4 | Size of Service Bay | 8.90 m x 4.00 m |
| 5 | Control Room | 5.45 m x 14.132 m |
| 6 | No. of Bay | 1 unit bay and one Service bay |
| 7 | No. of Units and Capacity | 1 Unit of 925 kW |
| 8 | El. of Turbine C/L | El 425.263 m |
| 9 | Generator Floor Level | El 426.863 m |
| 10 | Control Room, Service/Equipment handling Bay Level Floor Level | El 431.00 m |
| 11 | Draft Tube floor Level | El 422.34 m |
| 12 | Max TWL | El 425.292 m |
| 13 | Min TWL | El 424.416 m |
| Tail Channel | ||
| 1 | Length | 1073.00 m |
| 2 | Max. TWL | 425.292 m |
| 3 | Bed Width | 3.20 m |
| 4 | Side Slopes | 1:1.25 |
| 5 | Design Discharge | 9.55 cumecs |
| 6 | Bed Slope | 1 in 5000 (appx) |
| 7 | Bed Levels | Varying from 423.457 m to 423.242 m |
| Turbines | ||
| 1 | Type | Vertical Kaplan |
| 2 | Rated Output | 925 kW |
| 3 | Rated Head | 10.71 m |
| 4 | Rated Discharge per unit with COL | 10.51 cumecs |
| Out Door Yard | ||
| 1 | Size | 16.00 m x 38.00 m |
| 2 | No. of Power Transformers | 1 |
| Transmission Lines | ||
| 1 | Terminal Point | KPTCL 33KV sub-station at Arekere |
| Implementation Period | ||
| 1 | Implementation Period | 12 Months |
![]() |
![]() |
![]() |
![]() |