Bellary Solar Power Project `5 MW
LOCATION
1 State Karnataka
2 District Bellary
3 Village Bellary
Purpose of the Project
1 Purpose of the Project Generation and Transmission of Solar Electric Power
2 Power Scheme Solar Energy
Installed Capacity
1 Installed Capacity 5 x 1000 KW
Annual Energy Generation
1 Annual Energy Generation 7.57 GWHr
Area required for the Scheme
1 Area required for the Scheme 18.00 acres
Control Room
1 Type Surface type
2 Size of control room 26 m x 18m
PV Modules
1 Type Photo voltaic cell
2 Rated Output 180 Wp
3 Rated voltage 35.8 V
4 Rated current 5.03 A
5 Rated frequency 50 Hz
6 No. of modules required per MW 5576
7 Operating Temperature 80 deg C
8 Power Factor > 0.98
9 Array connected Series / Parallel
Power Conditioning Unit (Inverter)
1 Type Indoor
2 Rated Output Power 250 kW
3 Output AC Voltage 415 V
4 Frequency 50 Hz
Transmission Lines
1 Length 2 kms
2 Terminal Point 33kV/110kV KPTCL sub-station at Bellary- South
3 Type 33 kV Single Circuit Line
Out Door Yard
1 Size 50 m x 32.5 m
2 No. of Power Transformers 5 Nos. of 415V/33kV, 1250 kVA rating
Cost
1 Estimated cost of Civil Works Rs.502.00 Lakhs
2 Estimated cost of Solar Modules and Electrical works Rs.6488.00 Lakhs
3 Estimated cost of T –Transmission Rs.90.00 Lakhs
4 Cost at Completion Rs.7500.00 Lakhs
Energy
1 Total Energy Generation 7.57 GWHr
2 Saleable Energy 7.54 GWHr
3 Cost of Energy Generation (1st Year) Rs.16.21 per unit
4 Cost of Installation per MW Rs.1500 Lakhs
Implementation Schedule
1 Implementation Schedule 12 Months
 